AN OVERVIEW OF CONSTRUCTION OF QUARTERS FOR THE PERSONNEL OF
DEPARTMENTS OF POLICE, FIRE AND RESCUE SERVICES AND PRISON AND
OWN YOUR HOUSE SCHEME, BY TNPHC

i) Construction of Quarters for the Police Department:

Project

FS

Central
share

State
Share

No. of Quarters

No. of quarters constructed

 during the year under report

Rs. In crores

MPF

State

Phase XVI
(2000 Quarters)

142.23

 

142.23

 

2000

46

Phase XVII
(2000 Quarters)

136.93

10.83

126.10

148

1852

12

Phase XVIII
(3440 Quarters)

287.95

7.43

280.52

80

3360

20

Phase XIX
(4340 Quarters)

472.05

 

472.05

 

4340

350

Phase XX
(4800 Quarters)

476.07

 

476.07

 

4800

1289

MPF 2013 – 14

43.94

43.94

315 

78

MPF 2014 – 15

44.16

44.16

318

22

Part II 2010 – 11

1.63

1.63

7

1

Hon'ble CM's Announcement

107.33

 

107.33

 

699

133

Total

1712.29

107.99

1604.30

546

17058

1951


 (ii) Residential Quarters for the Police Department

Sl.
No.

Phase

No. of quarters Sanctioned

No. of quarters completed

Balance

Remarks

1

Phase I to XIII

28606

28606

0

Handed over

2

Phase XIV

2000

1975

25

Work to be taken up - 25 Nos.

3

Phase XV

2000

2000

0

Handed over

4

Phase XVI

2000

1884

116

Work in progress – 108 Nos.
Work to be taken up - 8  Nos.

5

Phase XVII

2000

1974

26

Work to be taken up - 26 Nos.

6

Phase XVIII

3440

3117

323

Work in progress – 323 Nos.

7

Phase XIX

4340

4106

234

Work in progress – 198 Nos.
Work to be taken up - 36 Nos.

8

Phase XX

4800

1991

2809

Work in progress – 1213 Nos.
Work to be taken up –1596 Nos.

9

Phase XXI

3000

3000

Work to be taken up – 3000 Nos.

10

Thirumullaivoyal

14

14

0

Handed over

11

MPF 2013 - 14

315

285

30

Work in progress –30 Nos.

12

MPF 2014 - 15

318

58

260

Work in progress –260 Nos.

13

Hon'ble C.M's
Announcement

699

191

508

Work in progress – 429 Nos.
Work to be taken up – 77 Nos.

14

CMRL

259

29

230

Work to be taken up - 230 Nos.

 

TOTAL

53791

46230

7561

 

(iii) Fire and Rescue Services Department:

So far the corporation has constructed 1107 quarters for the Fire & Rescue Services
Department as detailed below:

 

Year

No. of
quarters
sanctioned

No. of
quarters
completed

Balance

Remarks

1

1994-95
to
2002 - 03

937

937

-

Handed over

2

2010 - 11

225

183

42

Work in progress - 29 Nos.
Work to be taken up - 13 Nos.

3

 

18

 

18

Work to be taken up

4

CMA

147

28

119

Work in progress – 87 Nos.

Work to be taken up – 32 Nos.

 

TOTAL

1327

1148

179

 



(iv) Prison Department:

Sl.
No.

Year

No. of
quarters
sanctioned

No. of
quarters
completed

Balance

Remarks

1

1998-99 to
2005 - 06

516

516

-

Handed over

2

2001 - 02
to
2005 - 06

509

509

 

Handed over

3

2011 - 12

100

100

Handed over

4

2012 - 13

100

100

Handed over

5

2014 - 15

100

100 

Handed over

6

2015 – 16

100

30

70

Work in progress - 70 Nos.

7

CMA

1

1

Work to be commenced - 1 No.

 

TOTAL

1426

1355

71

 



(v) HOUSES UNDER OWN YOUR HOUSE SCHEME:
The corporation after revival has constructed 4644 quarters under "Own Your House" Scheme in various places as detailed below:

Sl .No.

Project

No. of units

Total Cost

(Rs. in lakhs)

1

Navalpattu

670

118.00

2

Ganapathy

432

194.00

3

Thimmarajapuram

387

201.01

4

Thorapadi

139

114.33

5

Vasanthapuram

114

345.83

6

Kotturpuram

38

200.63

7

Asoor (Near Kumbakonam) - Ph I

37

134.91

8

Maduravoyal

36

100.02

9

Velachery

32

84.44

10

Ayanpappakudi - Phase - I

26

135.60

11

Ayanpappakudi - Phase - II

24

87.91

12

Kundrathur

20

81.55

13

Asoor (Near Kumbakonam) - Ph II

16

137.86

14

Melakottaiyur

2673

45997.00

15

Thirupparankundram

24

568.00

16

Kulavanigarpuram

70

1644.75

 

TOTAL

4738

50145.84