ENTRUSTMENT OF WORKS UNDER MPF/11th FINANCE COMMISSION AND OTHER WORKS
AS ON 15-11-2006

SPILLOVER WORKS OF PREVIOUS YEARS AND ITS STAGE DURING THE CURRENT FINANCIAL YEAR 2005-2006.

 
 
Sl .No
Name of the Scheme
Mode of the Scheme/ Work
Authority
No.of.Works
Cost Rs.in lakhs
Stage of the Project
1
Phase XI (03 - 04) Deposit work G.O.MS.No.623 Home (Pol X) Dept Dtd: 29.07.2003 3000 11848 Work Completed - 2021 Qtrs. Work in Progress- 979 Qtrs
2
Police Academy Deposit work G.O.MS.No.309 Home (Pol X) Dept Dtd: 23.04.2005 1 4823 Work in progress
3
100 Police Station MPF 2002-03 G.O.MS.No.107 Home (Modern) Dept Dtd: 08.02.2002 100 1200 Workcompleted 96 Work in Progress - 4
4
Communication Complex for 4 Districts MPF 2002-03 G.O.MS.No.107 Home (Modern) Dept Dtd: 08.02.2002 1 28.75 Work under progress
5
Training center cum Barracks at chennai- 2 Places MPF 2003-04 1. G.O.MS.No.1307 Home (Modern) Dept Dtd: 05.12.2003 2. G.O.(3D) No 33 Home (Modern) Dept Dtd: 16.03.2004 2 144 G.O Received & work to be taken up.
6
Construction of Repeater station(Grey area)at 14 Places MPF (Utilisation of savings) G.O.2(D)No.123 Home (Modern)dept dtd 16.03.2004 14 25 Work dropped- 1 Work completed - 13
7
Construction of Administrative block, Bell of Arms,Gurad Room and Centry room for TSP VII Bn at Pochampalli MPF 2004-05 G.O.MS.No.1022 Home (Pol X) Dept Dtd: 19.08.2004 1 250.82 Work under progress
Work Undertaken during the Current Financial Year 2005-2006
1
Construction of 4000 Quarters during the year 2005-06 Deposit work G.O.MS.No.576 Home (Pol X) Dept Dtd: 08.07.2005 4000 17484 Work i n progress-2443 Work to be taken up - 1554 Qtrs Work Completed - 3
2
FSL - Head Quarters building MPF 2002-03 G.O.MS.No.624 (Pol X) Dept Dtd: 25.07.2005 1 600 Work under progress
3
FSL - Library Phase II MPF 2002-03 G.O.MS.No.570 Home (Modern) Dept Dtd: 26.01.2001 1 111 Tender stage
4
8 Police stations MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 8 175 Work under progress - 7 Work Completed - 1
5
Inservice Training center (Rs. 20.00 Lakhs each) MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 6 120 Work Completed - 4 Work under progress- 2
6
Community Hall Cum Training center at Pudukottai and Villupuram ( Rs.45.00 Lakhs each) MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 2 90 Work under progress
7
Construction of RFSL Building at Tirunelveli MPF 2004-05 G.O.MS.No.628 (Pol 18) Dept Dtd: 29.08.2005 1 90 Work under progress
8
Construction of Dormitory Barracks in Nilgiris District MPF 2004-05 G.O.MS.No.628 Home (Modern) Dept Dtd: 25.07.2005 1 75 Work under progress
9
DIG Range office(Rs.30.00 Lakhs each) Trichy and Villupuram MPF 2004-05 G.O.MS.No.191 Home (Pol X) Dept Dtd: 04.03.2005 G.O.MS.No.183 Home (Pol X) Dept Dtd: 04.03.2005 2 60 Work Completed
10
DPO (Rs.300.00 Lakhs each)(Perambalur, Tirunelveli & Namakkal) MPF 2004-05 G.O.MS.No.180 Home (Pol X) Dept Dtd: 02.03.2005. G.O.MS.No.182 Home (Pol X) Dept Dtd: 02.03.2005. G.O.MS.No.181 Home (Pol X) Dept Dtd: 02.03.2005. 3 900 Work under progress- 2 Work Completed - 1 (Tirunelveli )
11
Urban Police Station - 12 Nos MPF 2005-06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 12 262.44 Work under progress-8 Work to be taken up -4
12
Rural police station- 13 nos MPF 2005-06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 13 195 Work under progress - 13
13
Construction of Modern Control Room at salem and Trichy MPF 2004-05 G.O.MS.No.835 Home (Modern) Dept Dtd: 30.08.2005 2 80 Salem & Trichy Work in Progress
14
Construction of office for 4 zonal I.G.s MPF 2004-05 G.O.MS.No.110 (Pol X) Dept Dtd: 19.12.2005 4 100 Work in Progress - 2 work To be taken up - 2
15
DPO Karur MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 300 Work in Progress
16
Construction of Adminstrative Block, Armoury, Bell of Arms and Separate Barracks for men and women at Tamil nadu Special Batralian, Manimuthar MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 200 Work in Progress
17
Refurbising of PTC Library, Chennai MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 20 Tenders called for
18
Construction of Training center and class Room at PCCC at R.A .Puram, Chennai MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 50 Estimate under scrutiny
19
Construction of Training center and class Room at R.C.Avadi, Chennai MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 25 Work in progress
Proposed work on the pipe line
1
A.R.Complex at Erode MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 1 100 FS awaited from Government
2
Construction of new Dog kennel in chennai city at Vepery, Ambattur & St. Thomas Mount MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 1 6 21 Dog kennel - place to be identified 10 Dog kennel work to be taken up
3
a. Armoury for Nilgiris AR Complex MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 1 53 Work to be taken up
b. State Armoury Avadi MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 1 189 approval awaited from govt.
c. Tamil nadu Commando Force MPF 2004-05 G.O.MS.No.73 Home (Modern) Dept Dtd: 27.01.2005 1 12 approval awaited from govt.
4
DPO Krishnagiri MPF 2005 -06 G.O.MS.No.807 Home (Modern) Dept Dtd: 12.09.2005 1 300 Land to be identified
5
Coastal Security scheme Perspective Plan G.01.Lr.No.5/505/Coastal Security Ministry of H.A Dt: 27.12.2005 64 618.4 Feasibility studies are under progress